Hi Juyoung,
Thanks of your update. But based on the experience in Lotte store, it’s more realistic to open Galleria by the end of October.
Please find the below reason for your reference.
1, Due to the tight timing, PHE factory is agreed to keep production during summer vacation and try to shorten the lead time, but even though, the earliest arrival date to Korea would be around 10th Oct.
2, The site arrival date of Dform furniture would be around 10th Oct, but it depends on the quality of your drawings and when you can get approval, especially the site dimension part, which affects the furniture production.
3, The façade production only can be started after the shopdrawings and mock up are approval, which depends on your quality and the fastest time you can speed up.
Moreover, as per my email this morning, please add the setting out inspection date and interim inspection
date in your schedule. We need to clearly understand when your site condition is available for inspection.
Please be aware that, all the related works should be done before inspection. The setting out lining should
be full done before our setting out inspection, which is including the wall divisions, furniture positions and the whole RCP. And also, all the concealing work (MEP, HVAC, FS, etc) needs to be finished before interim inspection.
Could you please revise your schedule and send back to us tmr?
Thanks, Junhong.

Hi Juyoung,
Thanks for your update. However, based on the experience in Lotte store, it’s more realistic to open Galleria by the end of October.
Please find the below reason for your reference.
1, Due to the tight schedule, PHE factory has agreed / is in agreement to continue production during summer vacation and try to shorten the lead time, but despite this, the earliest arrival date to Korea would be around 10th Oct.
2, The site arrival date of Dform furniture would be around 10th Oct, but it depends on the quality of your drawings and when you can get approval, especially on the site dimension part as it affects the furniture production.
3, The façade production only can be started after the shopdrawings and mock up are approved / have approval, which depends on the quality and speed of your work.
Moreover, as per my email this morning, please add the setting out inspection date and interim inspection
date into your schedule. We need to clearly understand when your site condition is available for inspection.
Please be aware that, all the related work / tasks / jobs must be done before inspection. The setting out lining should be completely done before our setting out inspection, which includes the wall divisions, furniture positions and the whole RCP. As well as this, all the concealing work (MEP, HVAC, FS, etc) needs to be finished before the interim inspection.
Could you please revise your schedule and send it back to us tmr?
Thanks, Junhong.

Vocabulary

change my job switch companies / get a new job 

i’m weighing it up – considering things, judging the pros and cons (positives and negatives)

Please be aware that, it is crucial that all related work must be done before the inspection is able to be carried out.

even though it’s hot, I still want to go outside
It’s hot, but despite that, I still want to go outside

push back the date – make it later
bring forward the date – make it earlier

keep doing / continue doing / continue sth 

Grammar

she has been cooperating with our company for 3 years