VIP Class Notes (Jesse) [W]

Pronunciation

worm – “werm”

warm – “worm”

Vocabulary

i did my degree in Harbin

we can take crayfish tonight – we can have / eat crayfish 

bacteria – xi jun

Grammar

i have a computer that / which is black
i know (that) you are sad

i have what you want = i have the thing you want
i know what you want to drink = i know the drink you want to drink

with …. being
eg. I have many students with Hong being the smartest and most handsome
eg2. I love pizza with Italian being my favourite

Writing exercise

Hi Jessie,

Below is an email what I sent to my boss to clarify the schedule.

Hi Roy,

Please find the revised schedule in attached for your reference.

There are couple points in below to achieve the opening date on 11th Dec.
1, Only 2 times of site survey is allowed, especially the 2nd one needs to be very precise.
2, If site demolish could be completed before FFD should be much better. Normally the site condition before and after demolishing is different.
3, GC sampling needs to be approved completely by 2 times.

Moreover, please find the reason in below why it is hard to open on 2nd Nov.
1, Site survey needs to be very precise in one time. But as per experience on Samsung projects, site survey should be arranged by 2~3 times.
2, Site demolishing needs to be completed asap recently, in order to make sure site condition is match to design.
3, There would be 2~3 wks of summer holidays in Europe in August. Thus the lead time of PHE & Porro cabinets and other European purchasing items would be delayed by 2~3 wks.

Hi Jesse,

Below is an email (that) I sent to my boss to clarify the schedule.

Hi Roy,

Please find the revised schedule attached for your reference.

There are a couple of points below to (allow us) to achieve the opening date on 11th Dec.
1, Site surveying must be limited to 2 times / A maximum of 2 site surveys is allowed, with the 2nd one needing to be especially precise.
2, If the site demolish could be completed before FFD it would be much better. Normally the site condition before and after demolishing is different.
3, GC sampling must be correct by 2nd submission to ensure approval

Moreover, please find below the reason why it is hard to open on 2nd Nov.
1, Site survey needs to be very precise in one time / go / shot / the first time. But as per experience with Samsung projects, site survey should be arranged within 2~3 times.
2, Site demolishing needs to be completed asap these days, in order to make sure site condition matches design.
3, There will be 2~3 wks of summer holidays in Europe in August. Thus the lead time of PHE & Porro cabinets and other European purchasing items will be delayed by 2~3 wks.